Capital Improvement Projects in the Public Works Department include Major Road, Minor Road Improvements, Trails, Sidewalks & Stormwater Projects (under the Engineering Division), Signals & Traffic Safety Projects (Traffic Engineering Division) and Road Paving & Pavement Rehabilitation (Road Operation and Stormwater Division).

Use a map of Seminole County or 'My Resident Information' to find out which Commissioner District you are located in.

FILTER WHAT TO VIEW

COMMISSIONER DISTRICT: 
PROJECT TYPE:
PROJECTS STARTING WITH:

Printer-Friendly VersionPrinter-friendly List of All Projects

Go to page: 1 - 2 - 3 - 4 - 5 - 6 - 7 - 8 - 9 - 10 - 11 - 12

PROJECT ID
PROJECT  [Expand All - Close All]
00205749
17-92 MAST ARM CONVERSION (8 LOCATIONS)

Project Type: Traffic
Project Manager: Charles Wetzel III
Status: Active
Scope: THIS PROJECT WILL CONVERT EXISTING TRAFFIC SIGNALS ON US 17-92 TO MAST ARM SIGNALS AT THE FOLLOWING LOCATIONS: US 17/92 @ SR 434 US 17/92 @ AIRPORT US 17/92 @ SR 417 US 17/92 @ 27TH US 17/92 @ PARK US 17/92 @ 25TH US 17/92 @ 20TH US 17/92 @ 15TH
Phases:

  Construction                    Start: 6/2017 End: -

02207075
46A SIGNAL ADAPTIVE PROJECT (4 SIGNALS)

Project Type: Traffic
Project Manager: Charles Wetzel III
Status: Active
From: INTERNATIONAL PKWY
To: RINEHART RD
Scope: THIS PROJECT WILL PROVIDE ADAPTIVE TRAFFIC IMPROVEMENTS TO 4 SIGNALS FROM INTERNATIONAL PKWY TO RINEHART RD
Phases:

  Construction                    Start: -    End: -

01785406
5-POINTS SITE PLAN DESIGN & ARCHITECHUAL DESIGN

Project Type: Roadway Projects
Project Manager: Jeff Sloman
Status: Active
From: BUSH LOOP
To: COUNTY HOME ROAD
Scope: THIS PROJECT WILL BE TO STUDY AND DEVELOP A PRELIMINARY (30%) SITE PLAN AND PRELIMINARY ARCHITECTUAL DESIGN FOR MASTER SITE PLAN FOR 5PTS COUNTY COMPLEX. THIS WILL BE A SITE PLAN ONLY, NO BUILDING DESIGN WILL BE INCLUDED. PROJECT WILL BE ADMINISTERED BY THE ENGINEERING DEPARTMENT.
Phases:

  Design                          Start: 10/2016 End: 1/2020

02207083
ACCESS ROADWAY FS #39

Project Type: Roadway Projects
Project Manager:
Status: Active
Scope: NEW PROPOSED ROADWAY WILL PROVIDE CONNECTION OF EMERGENCY VEHICLES FROM FIRE STATION 39 TO INTERNATIONAL PKWY
Phases:

  Design                          Start: -    End: -
  Land                            Start: -    End: -
  Construction                    Start: -    End: -

01785444
ADA RETROFIT

Project Type: Roadway Projects
Project Manager: Michael Garcia - 407-665-5673
Status: Active
Scope: AS DIRECTED BY PAVEMENT MANAGEMENT PROGRAM, AS REQUIRED BY DOJ & FHWA ADA LAW
Phases:

  Design                          Start: 10/2018 End: 9/2019
  Construction                    Start: -    End: -

01785450
AIRPORT BLVD INT IMP

Project Type: Roadway Projects
Project Manager: Sam Moussa
Status: Active
From: W OF US 17-92
To: W OF SR 417
Scope: THIS PROJECT WILL ADDRESS SAFETY ISSUES AT SEVERAL INTERSECTION ALONG AIRPORT BLVD. LFA FDOT
Phases:

  Design                          Start: 11/2017 End: 4/2020
  Construction                    Start: 6/2020 End: -

00205207
ALT CITY COUNTY SHARED PEDESTRIAN OVERPASS

Project Type: Roadway Projects
Project Manager: Jean Jreij - 407-665-5602
Status: Active
From: N/A
To: N/A
Scope: CITY OF ALTAMONTE SPRINGS PROJECT FOR PEDESTRIAN OVERPASS.
Phases:

  Road Construction               Start: -    End: -

01785149
ALTAMONTE SUNRAIL BIKE/PED

Project Type: Roadway Projects
Project Manager: Matt Hassan
Status: Active
Scope: ADD BICYCLE AND PEDSTRIAN IMPROVEMENTS TO CONNECT TO THE SUNRAIL STATION COUNTY CONTRIBUTION TO CITY OF ALTAMONTE SPRINGS PROJECT TO ADD BICYCLE AND PEDESTIRAN IMPROVEMENTS TO CONNECT TO THE ALTAMONTE SPRINGS RUNRAIL STATION. $2M IDENTIFIED ON THE TAX LIST AND ALLOCATED PER INTERLOCAL AGREEMENT
Phases:

  Design                          Start: 10/2017 End: 9/2019
  Construction                    Start: -    End: -
  Aid To Govt Agencies - Design   Start: -    End: -
  Aid To Govt Agencies - Constr.  Start: -    End: -

01785521
ALTON DR STORMWATER POND MOD

Project Type: Stormwater
Project Manager: Shannon Wetzel - 407-665-2455
Status: Active
Scope: MODIFY EXISTING POND, INCREASE TREATMENT EFFICIENCY, LOSE TO LAKE ASHER. CONSTRUCTION RETROFIT PROJECT (FY16/17 - DESIGN & PERMITTING; FY17/18 - CONSTRUCTION)
Phases:

  Construction                    Start: -    End: -

01785434
ALTON DRIVE STORMWATER POND MODIFICATION

Project Type: Stormwater
Project Manager: Shannon Wetzel - 407-665-2455
Status: Completed
Scope: MODIFY EXISTING POND, INCREASE TREATMENT EFFICIENCY, CLOSE TO LAKE ASHER. CONSTRUCTION RETROFIT PROJECT (FY16/17 - DESIGN & PERMITTING; FY17/18 - CONSTRUCTION)
Phases:

  Design                          Start: 1/2017 End: 3/2019
  Construction                    Start: 9/2019 End: 10/2019

02104043
AMENITIES FOR TRAILHEADS/BIG TREE PARK AND GREENWOOD LAKE TRLHD

Project Type: Trail Projects
Project Manager:
Status: Pre-Project
Scope:
Phases:

  Design                          Start: -    End: -

01785448
ANNUAL BRIDGE REPAIR-MAJOR

Project Type: Bridge Repair
Project Manager: Sam Moussa
Status: Active
Scope: MAJOR BRIDGE REPAIR AS NEEDED - COUNTYWIDE
Phases:

  Design                          Start: -    End: -
  Construction                    Start: -    End: -

01785447
ANNUAL BRIDGE REPAIR-MINOR

Project Type: Bridge Repair
Project Manager: Sam Moussa
Status: Active
Scope: THIS PROJECT TRACKS THE BRIDGE REHABILITATION AND REPAIR EXPENDITURES NECESSARY TO CORRECT DEFICIENCIES IN COUNTY MAINTAINED VEHICULAR BRIDGES THAT WERE IDENTIFIED AND REPORTED TO THE COUNTY BY THE STATE OF FLORIDA. THIS PROJECT ALSO TRACKS THE BRIDGE INSPECTION, REHABILITATION AND REPAIR EXPENDITURES FOR ALL PEDESTRIAN OVERPASSES OR TUNNELS.
Phases:

  Design                          Start: 10/2018 End: 9/2019
  Construction                    Start: -    End: -

00137101
ASPHALT SURFACE AND PAVEMENT MANAGEMENT - NEW

Project Type: Rehabilitation
Project Manager: Aaron Johnson
Status: Closeout Transition
From: VARIOUS LOCATIONS
To: VARIOUS LOCATIONS
Scope: ASPHALT OVERLAY, FULL DEPTH RECLAMATION, AND VARIOUS METHODS OF ASPHALT SURFACE REFURBISHMENT THAT ARE APPLIED TO SEMINOLE COUNTY'S PAVED ROAD NETWORK. THIS INCLUDES LOCAL ROAD RESURFACING AND REHABILITATION THAT MAY INVOLVE RECONSTRUCTION ACTIVITY. THIS ALSO INCLUDES RESURFACING OF ARTERIAL/COLLECTOR ROADS NOT INVOLVING THE ROADWAY BASE.
Phases:

  Road Construction               Start: 10/2007 End: -

01785224
ASSET MGMT INSP & INV

Project Type: Construction Management
Project Manager: Michael Garcia - 407-665-5673
Status: Active
Scope: PROJECT WILL IDENTIFY ASSET CONDITION,AGE,HISTORY, AND RECOMMEND A REPLACEMENT SCHEDULE BASED ON A CONDITION RATING SYSTEM.
Phases:

  Construction                    Start: -    End: -

00205742
ATMS VIDEO DETECTION PROJECT

Project Type: Traffic
Project Manager: Steven Douglas - 407-665-5684
Status: Active
Scope: INSTALLATION OF VIDEO DETECTION FOR SEVERAL TRAFFIC ADAPTIVE SIGNAL SYSTEMS RELATED TO METROPLAN AND FDOT ATMS PHASE II PROJECT.
Phases:

  Road Construction               Start: 10/2013 End: 9/2014

01785167
ATMS/ITMS PROGRAM

Project Type: Roadway Projects
Project Manager: Charles Wetzel III
Status: Active
Scope: EXHIBIT B COUNTY LIST - ADVANCED TRAFFIC MANAGEMENT SYSTEM (ATMS) AND INTELLIGENT TRANSPORTATION SYSTEM (ITS) IMPROVEMENTS. PRELIMINARY COSTS $11M. PROJECTS INCLUDE BUT ARE NOT LIMITED TO FIBER UPGRADES, ADAPTIVE SIGNAL SYSTEM., VARIABLE MESSAGE SIGNS(VMS) BLUETOOTH TRAVEL TIME READERS AND OTHER FUTURE NEW ITS TECHNOLOGY ON ARTERIAL AND COLLECTOR ROADWAYS.
Phases:

  Construction                    Start: 1/2017 End: -

01907061
AZALEA AVE SIDEWALKS

Project Type: Sidewalk Program
Project Manager: Angela Cardona
Status: Closeout Transition
From: LAKEMONT AVE
To: END OF ROAD
Scope: THIS PROJECT WILL CONSTRUCT SIDEWALKS ALONG AZALEA AVE
Phases:

  Design                          Start: 4/2019 End: 10/2019
  Construction                    Start: 5/2021 End: -

02207106
BALMY BEACH DR @ WALMART MAST ARM

Project Type: Traffic
Project Manager: Charles Wetzel III
Status: Active
Scope: MAST INSTALLATION WHICH ALSO INCLUDES ADDITIONAL WORK AT WALMART DRIVEWAY (ESCROW AGREEMENT $108,654)
Phases:

  Construction                    Start: -    End: -

02207094
BASIN STUDIES - EAST COUNTY

Project Type: Stormwater
Project Manager: Jeff Sloman
Status: Active
Scope: BASIN STUDIES/ GEE CREEK $296,250, HOWELL CREEK - $474,000, LK JESUP -$692,250, LITTLE LK HOWELL-$266,250, ST JOHNS -$296,250, PUZZLE LAKE-$266,250

01785921
BEACON DR RECONSTRUCT - HURRICANE IRMA

Project Type: Construction Management
Project Manager: Calvin Landers
Status: Active
Scope: HURRICANE IRMA DAMAGED THE ENTIRE ROADWAY .17 MILES
Phases:

  Construction                    Start: -    End: -

02207092
BEAR GULLY MODEL UPDATE (STUDY)

Project Type: Stormwater
Project Manager: Shannon Wetzel - 407-665-2455
Status: Active
Scope:

02207088
BEAR LAKE RD

Project Type: Rehabilitation
Project Manager:
Status: Active
From: BUNNELL RD
To: SR 436
Scope: RECONSTRUCTION OF ROADWAY- REPLACEMENT PROJECT
Phases:

  Construction                    Start: -    End: -

01785561
BENEFIT COST STUDY

Project Type: Roadway Projects
Project Manager: Anthony Nelson - 407-665-5763
Status: Active
Scope: THIS STUDY WILL DEFINE PROJECTS AND ANY ALTERNATIVES, THEN BY IDENTIFYING, MEASURING, AND VALUING THE BENEFITS AND COSTS OF EACH.

01785231
BIG WEKIVA BASIN MASTER STUDY

Project Type: Stormwater
Project Manager: Kimberly Ornberg - 407-665-2012
Status: Active
Scope: BASIN EVALUATION INCLUDING HYDROLOGIC AND HYDRAULIC MODELING AS WELL AS POLLUTANT LOADING ANALYSIS.
Phases:

  Design                          Start: 12/2016 End: 2/2020

Go to page: 1 - 2 - 3 - 4 - 5 - 6 - 7 - 8 - 9 - 10 - 11 - 12

Total Number of projects: 286

State ProjectsLooking for state roadway projects? Visit the Florida Department of Transportation's (FDOT) page or utilize the FDOT District 5 Interactive Mapping and Reporting Application.