PROJECT ID |
|
|
N RONALD REAGAN BLVD
Project Type: Paving
Project Manager:
Status: Pre-Project
From: COUNTRY CLUB RD
To: US 17-92
Scope: WORK ASSOCIATED WITH FULL DEPTH RECLAMATION, ASPHALT OVERLAY, AND VARIOUS REHABILITATION TASKS. (I.E. PIPE LINING OR REPLACEMENT) SHOULDER RESTORATION
|
|
N RONALD REAGAN BLVD 2022
Project Type: Roadway Projects
Project Manager:
Michael Garcia - 407-665-5673
Status: Active
From: LONGWOOD LAKE MARY RD
To: S COUNTRY CLUB RD
Scope: RECONSTRUCTION OF ROADWAY
Phases:
Construction Start: - End: -
|
|
N RONALD REAGAN BLVD/ CR 427 RESURFACING PROJECT
Project Type: Paving
Project Manager:
Michael Garcia - 407-665-5673
Status: Active
From: COUNTRY CLUB RD
To: US HWY 17-92
Scope: WORK ASSOCIATED WITH FULL DEPTH RECLAMATION, ASPHALT OVERLAY, AND VARIOUS REHABILITATION TASKS.
Phases:
Construction Start: 9/2019 End: -
|
|
NARCISSUS AVE ROADWAY IMPRO
Project Type: Roadway Projects
Project Manager:
Leo Bonilla
Status: Active
Scope:
Phases:
Design Start: - End: - Construction Start: - End: -
|
|
NEBRASKA AVE BRIDGE DRAINAGE HMGP
Project Type: Stormwater
Project Manager:
Tuan Huynh
Status: Active
From: NEBRASKA AVE
To: MISSOURI AVE
Scope: NEBRASKA AVENUE BRIDGE, LOCATED ON THE CORNER OF NEBRASKA AVENUE & MISSOURI AVENUE. GPS COORDINATES - 28.834, -81.336.
AS THE CANAL APPROACHES THE ST. JOHN'S RIVER, THE ELEVATIONS DECREASE AND THE CANAL BECOMES SHALLOWER UNTIL THE BANKS BEGIN TO DISAPPEAR INTO THE WETLANDS ADJACENT TO THE RIVER. NORTH OF HOIO AT NEBRASKA AVENUE THERE IS A CONCRETE BRIDGE STRUCTURE BUILT OVER THE CANAL BY A PRIVATE DEVELOPER APPOX. 40 YEARS AGO. IT HAS A SPAN FEET AND VERTICAL CLEARANCE OF APPROX. 4 FEET. DURING HEAVY CANAL FLOWS, THE BRIDGE IS OVERTOPPED, WITH WATER FLOODING NEBRASKA AVENUE, SPILLING ONTO MISSOURI AVE, AND CREATING EROSION AND SEDIMENTATION PROBLEMS IN THE VICINITY OF THE STRUCTURE.
Phases:
Design Start: - End: - Construction Start: - End: -
|
|
NEBRASKA AVE DRAINAGE-HMGP GRANT
Project Type: Rehabilitation
Project Manager:
Tuan Huynh
Status: Active
Scope:
Phases:
Design Start: - End: -
|
|
NETWORK CORE ROUTERS UPGRADE
Project Type: Traffic
Project Manager:
Charles Wetzel III
Status: Active
Scope: FIBER OPTIC UPGRADE/ INCREASING CAPACITY OF THE FIBER OPTIC NETWORK
Phases:
Construction Start: - End: -
|
|
NETWORK SWITCH UPGRADE
Project Type: Traffic
Project Manager:
Charles Wetzel III
Status: Active
Scope: NETWORK SWITCH UPGRADE
Phases:
Construction Start: - End: -
|
|
NEW CABINETS/UPGRADES
Project Type: Traffic
Project Manager:
Charles Wetzel III
Status: Active
Scope: NEW AND TS1 TO TS2 REPLACEMENTS (W/ AND W/OUT UPS) AT YEAR END THE PROJECT MANAGER WILL PROVIDE BREAKDOWN OF COST BY LOCATION FOR CAPITALIZATION PURPOSES
Phases:
Construction Start: - End: -
|
|
NEW OXFORD RD WIDEN
Project Type: Roadway Projects
Project Manager:
Dennisse Zornan - 407-665-5670
Status: Active
From: SR 436
To: US HWY 17-92
Scope: THIS PROJECT WILL WIDEN APPROXIMATELY 0.5 MILES OF OXFORD RD FROM 2 TO 4 LANES AND IT WILL EXTEND THE ROADWAY AS ADDITIONAL 0.5 MILES TO US HWY 17-92.
PRELIMINARY ENGINEERING AND WETLAND MITIGATION FOR THE OXFORD RD RECON AND EXT PROJECT. PROJECT WILL BEGIN AT US 17/92 AND PRAIRIE LAKE DR AND CONTINUE EAST WITH NEW CONSTRUCTION, UNTIL IT MEETS THE INTERSECTION OF FERN PARK BLVD AND OXFOR RD. CONTINUE NORTH FOR APROOROXIMATE DISTANCE OF 1700 FT WHERE IT WILL TERMINATE AT THE SR 436 AND OXFORD RD INTERSECTION.
Phases:
Design Start: 1/2014 End: 12/2019 Land Start: 11/2016 End: 12/2019 Construction Start: - End: - Road Construction Start: 9/2019 End: -
|
|
NOLAN RD CHANNEL DRAINAGE HMGP
Project Type: Stormwater
Project Manager:
Tuan Huynh
Status: Active
From: SIX MILE CREEK
To: SANFORD AVE DITCH
Scope: SIX MILE CREEK AND SANFORD AVENUE DITCH, GPS COORDINATES - 28.736, -81.280, LOCATED BY 5050 NOLAN ROAD, SANFORD
THIS PROJECT WILL INCREASE THE CAPACITY OF THE NOLAN ROAD CROSSING BY REPLACING THE EXISTING CULVERT AND REGRADING THE ASSOCIATED CHANNEL IN ORDER TO PREVENT ROAD OVERTOPPING. THIS WILL ALSO CONTRIBUTE TO SEMINOLE COUNTY'S OVERALL WATER QUANTITY AND QUALITY GOALS FOR THE LAKE JESUP BASIN WHILE REDUCING LOCALIZED FLOODING AND ROADWAY OVERTOPPING IN A NEIGHBORHOOD THAT HAS EXPERIENCED SIGNIFICANT FLOODING WITH THE INCREASE IN MAJOR STORM ACTIVITY IN CENTRAL FLORIDA. UPON IMPLEMENTATION, THE NOLAN ROAD CULVERT WILL MEET THE COUNTY'S 25-YEAR/24-HOUR DESIGN STORM LEVEL OF SERVICES ASSIGNED TO ITS PRIMARY DRAINAGE SYSTEM, THE PRIMARY FOCUS OF WHICH IS PUBLIC SAFETY BY PROTECTION AGAINST FLOODING OF HOUSES/BUILDINGS AND MAINTAINING EMERGENCY AND EVACUATION ROUTE ACCESS.
Phases:
Design Start: - End: - Construction Start: - End: -
|
|
NOLAN RD DRAINAGE-HMGP GRANT
Project Type: Rehabilitation
Project Manager:
Tuan Huynh
Status: Active
Scope:
Phases:
Design Start: - End: -
|
|
NORTH ST CORRIDOR IMP
Project Type: Roadway Projects
Project Manager:
Bill Wharton
Status: Active
From: CR 427
To: PALM SPRINGS DR
Scope: NORTH ST/PALM SPRINGS DR TO RAYMOND AVE / 6 PROJECTS IN THIS PROJECT 1-RAYMOND AVE -FROM NORTH ST TO SR 434 / PROJECT 2 - NORTH ST-FROM RAYMOND AVE TO PALM SPRINGS /PROJECT 3-PALM SPRINGS DR FROM NORTH ST TO SR 434 / PROJECT 4 -PALM SPRINGS DR FROM CENTRAL PKWY TO NORTH ST / PROJECT 5 - NORTH ST FROM PALM SPRINGS DR TO LONGWOOD CITY LIMITS/ PROJECT 6 - NORTH ST FROM LONGWOOD CITY LIMITS TO CR 427
Phases:
Design Start: 3/2019 End: 12/2019 Construction Start: - End: -
|
|
NORTHWESTERN /LITTLE WEK BRIDGE
Project Type: Bridge Repair
Project Manager:
Leo Bonilla
Status: Active
From: NORTHWESTERN AVENUE
To: LITTLE WEKIVA RIVER
Scope: THIS PROJECT WILL CONSTRUCT A BRIDGE OVER THE LITTLE WEKIVA RIVER TO REPLACE THE EXISTING BRIDGE THAT HAS BEEN DETERTMINED FUNCTIONALLY OBSOLETE.
Phases:
Design Start: 8/2016 End: 6/2019 Construction Start: 10/2019 End: -
|
|
NRCS-IRMA-SALES TAX PROJECTS (LUMP SUM IN DB)S
Project Type: Stormwater
Project Manager:
Owen Reagan - 407-665-5946
Status: Active
Scope: THIS IS THE SALES TAX MATCH FOR THE NRCS GRANT . PLEASE SEE THE DETAILED LISTING OF SPECIFIC PROJECTS AND BAR FOR SUBLEDGER NUMBERS.
Phases:
Construction Start: - End: -
|
|
NUTRIENT/HYDR STUDY FOR LK MILLS AND SURROUNDING LAKES
Project Type: Stormwater
Project Manager:
Status: Active
Scope: CONDUCT NUTRIENT SOURCE TRACKING AND PROVIDE LAKE MANAGEMENT
RECOMMENDATIONS FOR THE LAKES.
NUTRIENT/HYDR STUDY FOR LK MILLS AND SURROUNDING LAKES(KIWINAS-EMERALD-SPRING-CATHERINE
|