Wet Tap/Line Stop Inspection for Seminole County Utilities

Wet tap inspection requires a 72 hour advanced notice Monday through Thursday and between the hours of 8:00 AM and 2:00 PM. No wet taps or line stops will be done on Fridays.

     
* Indicates Required Field

Project Name   *
 

Contractor & Phone #   *
 

Contractor Email   *
 

Subcontractor & Phone #   *
 

Engineer   *
 

Utility Permit #
 

Right of Way Permit # (if applicable)
 

MOT Index #   *
 

811 Locate Ticket #   *
 

County Inspector   *
 

Water Main Tap Size
 

Force Main Tap Size
 

Reclaim Main Tap Size
 

Inspection Date Requested


Date Requested (MUST BE 72 HOUR NOTICE)   *
 

Time Requested   *
 

Contractor’s Responsibilities


1. Install dewatering, sheeting, bracing or shoring (if required)

2. Verify tapping sleeve is per Seminole County detail and Approved Materials list

3. Tapping sleeve to be located a minimum of 4’ from any pipe joints, fittings or valves

4. Add #57 stone per Seminole County details

5. Install pressure gauge & perform pressure test (150 psi for 15 minutes)

6. Tapping valve and machine are to be supported properly & not cause undue stress on the main

7. Deliver pipe coupon to Inspector

8. Backfilling & compaction of excavated area

9. Restoration as required

It is recommended to have the 2” taps installed for the jumper assembly if the wet tap is installed on a Potable Water Main line.